Carillion, Greenwood Academy, Castle Vale, Birmingham
![]() | ![]() | ![]() |
---|---|---|
![]() |
We are in the process of completing the construction of a brand-new academy in Castle Vale Birmingham as part of the PF2 Midlands scheme, for Carillion building limited.
The construction of the new academy involved:
-
A major earthworks operation to remove contaminated material from the old Spitfire factory that was on the site.
-
The construction of a large raft foundation with over 1000m3 of concrete in, one pour alone consisted of over 600m3.
-
Drainage works incorporating a large attenuation crate system
-
A new multiuse games area.
-
The foundations and associated works for a new sports centre and energy centre.